Paving projects

Paving projects

Work began earlier this month as more than 28 miles of roads will be resurfaced in Independence Township.
The first road to be resurfaced is Andersonville Road from Old White Lake Road east to the southern township border. Work began May 8.
The following roads will also be resurfaced this year: Sashabaw Road, from Maybee Road to the township border; Clintonville Road, from Maybee Road to Mann Road, Waldon Road, from the Clarkston Village border to Clintonville Road (expected to start in June); Sashabaw Road, from south of Clarkston Road (near DTE Energy Music Theatre) to Oak Hill Road (township border) which expected to start in June; Clintonville Road, from Waldon Road to Clarkston Road, expected to start in July; and Clintonville Road, from Maybee Road to Waldon Road, expected to start in August.
All work is being paid for mostly by a special property tax millage that was approved by township voters in 2018 for this specific purpose.

Leave a Reply

Your email address will not be published.